When datacenters lose power, generators should kick in. That didn’t happen for Google in London
· theregister.com · popularity 21/100 · 0 similar stories today

Read the original at theregister.com →
Summary
October outage caused by bad PLC config exposed at a time maintenance work reduced resilience
Found in: The Register. Rating basis: single outlet; outlet tier 2 (unlisted); 1 feeds; feed position 1.