EVOVX News Index

Lanarkshire AI datacentre to fully rely on National Grid despite renewables claim

· theguardian.com · popularity 29/100 · 0 similar stories today · Nuclear Energy (Energy & Climate Tech)

Read the original at theguardian.com →

Summary

DataVita has revised plan for Chapelhall development to be wholly powered by 1GW of renewable energy A datacentre company that said it would power a massive AI development near Glasgow with renewable energy has admitted that the scheme will be entirely served by the National Grid. DataVita, a key plank of the UK’s AI strategy, had promised that the Lanarkshire project would draw 1GW – the equivalent output of a small nuclear reactor, or Britain’s largest windfarm – from green sources. But when the Guardian raised questions about the pledge , it said the arrangement was “subject to final commercial agreements, planning, grid and consenting processes”. Continue reading...

Found in: Guardian World. Rating basis: single outlet; outlet tier 5; 1 feeds; feed position 38.